APPLICATION
FlowTech INC., Zhejiang
A data center in Wuzhen
This project is applied to a data center in Wuzhen. The project adopts Futeng Fluid 300RT air flotation centrifugal chiller (single head)
Application field: data center
Project Status:
1. The project is the first batch of distributed storage data centers in China, with appropriate granularity, which will be put into operation in batches and gradually put into operation;
2. The equipment is put into operation according to the full load of 2100kW, and 2+1 300RT air flotation centrifugal chillers (single head) are used;
3. The initial load is 300-500kW, which can be satisfied by opening one;
4. It will be launched in October 2020.